DSDM Agile project management cheat sheet

Spreadsheet
Matrix of product phases and products, indicating who is responsible for what.

Just over a year ago I was sitting in a classroom learning about and sitting two exams on DSDM Atern Agile project management.

Something that I wished had been available at the time was some kind of cheat sheet that broke down each of the DSDM phases (pre-project, feasibility, foundations, exploration, engineering, deployment, and post-project), indicated which products (usually documents) belonged to which phase, and who was involved in the creation of each product.

I couldn’t find anything suitable, so I created my own, pulling out all that information from appendix C of the DSDM Agile Project Management Handbook into a RACI matrix.

Over the last year I’ve found this to be a really useful resource. I have it printed out on A3 and stuck on the wall next to my desk; I refer to it a lot.

You’re welcome to use it and adapt it for your own needs: 

Velocity and why it’s important

Fast car
We’d like to develop websites that fast, please

Velocity is an important tool in Agile. Let me explain a little about what it is and why we find it useful.

Speed equals distance over time

One of the challenges when planning each two weeks’ sprint is working out how much work we can realistically commit to. That’s where estimates and velocity work together.

Since we estimate each task (using ideal hours), at the end of each sprint we can count up the values of all the tasks that we completed (only those that landed safely in the DONE column in Trello—that is tasks that have been both completed and successfully tested) to reveal our velocity for that sprint: how much value we were able to deliver to the project (or projects) during that two weeks’ timebox.

In theory that should then tell us how much we ought to expect to complete during the next sprint.

But it doesn’t always work like that.

Continue reading Velocity and why it’s important

Planning poker—why and how we estimate

Planning poker cards
All the tools you need to become an Agile planning ninja

When creating a plan—whether it be a big project release plan or a smaller two-weeks’ timebox plan—you essentially need to know three things:

  1. Tasks —What are the requirements? What do you need to do?
  2. Size — How big are these tasks compared with one another? How long will these take to complete?
  3. Priorities — Which tasks need to be done first because others depend on them? Which tasks are most important regardless of dependencies?

It’s very much like creating a recipe: assemble the right ingredients, measure them to the correct proportions, and then mix them together in the right order.

In an Agile project the prioritisation of tasks is done by the business. It is their project after all; they have the most information about value, they understand the market, they have an idea of what features should be delivered next. Prioritisation is not a decision to be made by the development team.

The size of each task, however, is something that the development team is qualified to estimate. If I want a new wall built in my garden whose estimate should I trust more: mine (the person who commissions the work) or the builders (who do this job day-in, day-out for a living)?

When planning, we use a tool called planning poker to help estimate the relative size of tasks.

Continue reading Planning poker—why and how we estimate

Agile release planning with multiple projects

One of the biggest challenges we faced when we started down the Agile path was how to accommodate working on multiple projects concurrently. This is a little insight into how we are currently managing ourselves across two projects plus business as usual tasks.

The Agile ideal

Most Agile/XP/Scrum literature assumes a single, cross-functional team working on a single project for a single customer using a narrow range of technical disciplines. The primary reason for this is that task-switching is really expensive: it is much more efficient to remain focused on one project.

That way of working, though attractive, is more or less impossible in our situation; something that I’ve also heard from other university digital teams. We don’t just work on projects, we have business as usual commitments (which include meetings, support calls, personal development, blogging, editorial calendar updates, etc.), consultancy (where we work on approved institutional-priority projects managed by other teams) and portfolio mechanics (board meetings and related admin, writing up project ideas and terms of reference documents, etc.).

After all that excitement has been deducted from our working week, we are generally left with only about 40% of our time to dedicate to pushing projects towards completion. We therefore need to be careful to extract as much value as we can.

Continue reading Agile release planning with multiple projects

The challenges of resource management in our Agile team

Over the last year, as we’ve been formally trying to work in a more agile way, one of the biggest challenges I’ve faced as a project manager is resource management. In other words,

  1. How do we know how much time each team member has to work on projects?
  2. When we’re planning the next sprint, how do we track how much work has been assigned to a team member, so that they have neither too little nor too much work.

Agile planning in theory

In theory, Agile planning should be pretty straight forward.

Imagine we have a team of five developers, each with 6 hours available for work each day. That gives us 30 hours per day, and assuming 9 days of project work (with one full day set aside for retrospective and planning) then within each two weeks sprint we should be able to dedicate 270 hours to development work.

During the planning session then, with the business having prioritised the work to be done next, it’s up to the development team to estimate the size of tasks and stack these up in a backlog. We know that we should aim for around 270 hours of work (or perhaps a little less, maybe 265 hours, to create some slack — breathing room to make provision for some tasks running on a bit longer than anticipated).

Moving through the sprint, developers pull work to themselves and gradually over the fortnight all 265 hours of work is completed.

Within a few sprints the team begins to establish a velocity—the average amount of work that can be comfortably completed. This really helps to plan further ahead as the team becomes both more predictable and reliable.

Continue reading The challenges of resource management in our Agile team